Completition of sewage network of the agglomeration Bardejov

Veolia

Completition of sewage network of the agglomeration Bardejov

Beginning of construction: August 2015

Date of completion: September 2015

Cost of technological part: 49 300 €

The construction consisted of completion of sewerage networks in the municipality of Bardejov - the district Poštárka; streets: Pod Kalváriou, Poštárka, Pod Lipkou, Kacvinská, Bardejovská Zábava Pod Dubinami.

Scope of work: Supply and assembly of technological and electro technical parts of 7 pumping stations. In each of the PS there are 2 sludge pumps with a cutting device. One pump serves as a 100% reserve. The construction of sewerage and water supply in the Bardejov agglomeration ensured an increase in the standard of living of the population, the development of provided services and the protection of the environment.